You can print task reports from anywhere in Project KickStart, though it makes the most sense to print them after you have developed your tasks and arranged them in a sensible order.

Before you print task reports, you might want to widen the Task Name column in the Task List to make sure you print the complete task information. (Drag the splitter bar next to the Task Name column heading.)

To print a task report:

  1. Click File on the menu bar, and then click Print Task Reports. In the Tasks step, you can click the Print Reports button instead.

The Create and Print Task Reports dialog box opens.

  1. Click the list arrow and then click Task Report, Individual Assignments, or Phases, Goals, People & Obstacles.
  2. Select the information you want to include in the report, as described below.
  3. Preview the report and change the page setup as necessary. (See Print Preview and Page Setup.)
  4. Click the Print button.

Task Report

The Task report covers the entire project, and includes the Task Name and other details you select.


  1. Select the data columns you want to display in the report.

Click to insert or remove a checkmark from the box for each detail.

  1. Select the date range for the report.

By default, the report prints the entire range of tasks. Click the Start or Finish list arrow to display a calendar you can use to select a different start or finish date.

  1. Choose which tasks to display in the report.

By default, the report prints all tasks. Click the Incomplete Tasks or Completed Tasks option button to focus on one type of task.

  1. Click the Preview button. (See Print Preview for details.)

Individual Assignments

The Individual Assignments report covers the entire project, and lists the tasks assigned to each resource. The report  includes the Task Name and other details you select.

  1. Select the data columns you want to display in the report.

Click to insert or remove a checkmark from the box for each detail.

  1. Select the date range for the report.

By default, the report prints the entire range of tasks. Click the Start or Finish list arrow to display a calendar you can use to select a different start or finish date.

  1. Choose which tasks to include in the report.

Click the All Tasks, Incomplete Tasks, or Completed Tasks option button.

  1. Choose which people to include. The report lists tasks assigned to the people you select.

Click to insert or remove a checkmark from the box for each person.

  1. Click the Preview button. (See Print Preview for details.)

Phases, Goals, People & Obstacles

This report includes the phases, goals, people, and obstacles in your project. You can include some or all of these items in the report.

  1. Select the data columns you want to display in the report.

Click to insert or remove a checkmark from the box for each detail.

  1. Click the Preview button. (See Print Preview for details.)


Tip

See Also

  Print Gantt Chart Reports