This feature is available only in Project KickStart Professional.
In the Schedule step, you work in the Gantt chart to set start and finish dates for your tasks and refine your project plan. To make scheduling easy and quick, Project KickStart provides a starter schedule for new projects by setting today as the start date and assigning a one-day duration to each task. This creates a waterfall or cascade pattern, with one task following the other.
In addition, Project KickStart Pro links the tasks for you, so when you open the Gantt chart, you see a linked waterfall similar to the one shown below. Besides providing a schedule that starts in a cascade with each task lasting one day, each task is linked to the next task.

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view in the right pane. To adjust the schedule to fit your project, set the project start date in the toolbar, move and resize the taskbars in the Chart view, or change the start and finish dates or durations of individual tasks in the Task Data view. See About Scheduling Tasks for details.
Next, fine-tune the dependencies in your project by you can linking and unlinking tasks, changing their predecessors and successors, and setting lead times. For example, if one task is not dependent on another, you can unlink the tasks. If another task can’t start until two other tasks are finished, you can add a predecessor to that task, in which case the two tasks will be linked.
To link tasks:
To select two or more adjacent tasks, hold down the Shift key and then click the tasks. To select two or more nonadjacent tasks, hold down the Ctrl key and then click the tasks.
The tasks are linked so that the first task is the predecessor to the second task, the second task is the predecessor to the third task, and so on.
To unlink tasks:
To select two or more adjacent tasks, hold down the Shift key and then click the tasks. To select two or more nonadjacent tasks, hold down the Ctrl key and then click the tasks.
The tasks are no longer linked.
To fine-tune the linked tasks: